Austrian interior ministry and APG sign cooperation agreement on blackout prevention

Austrian interior ministry and APG sign cooperation agreement on blackout prevention

On 27 September 2021, the Ministry of the Interior signed an agreement on blackout preparedness with Austrian Power Grid (APG).

This formalises the long-standing cooperation in the APG control centre. The cooperation agreement sets out the concrete procedure in the event of a blackout. While APG is responsible for a secure power supply and, in the worst case, for rebuilding the power grid, the police must continue to ensure the safety of the population in a crisis. In addition, the Ministry of the Interior (BMI), as the security ministry, must coordinate the authorities’ measures in crises and disasters.

“A blackout is one of the greatest threats to modern states. Without electricity, security of supply, transport, communication and – not least – public security are under threat. […] Our plans provide for the police to be able to hold out for 72 hours and to guarantee emergency operation for a further four days. The agreement with APG gives us a decisive information advantage in a crisis and ensures that communication between these key players does not break down.”

Karl Nehammer

Karl Nehammer

BMI, Minister of the Interior

Planning games and crisis exercises

APG board members Gerhard Christiner and Thomas Karall struck the same note: “In the event of an imminent or actual blackout, this contract gives us, and therefore Austria, more security. It sets out the processes and procedures for a crisis. Key elements such as joint situation reports, crisis exercises and clear default behaviour are now formalised and written down. A clear crisis plan is an important step towards reacting correctly in a stressful situation, even though our staff practise emergencies very often in numerous crisis simulation trainings.”

APG is also involved in planning games and crisis exercises with the BMI. “In a crisis, it is about everyone involved knowing their contacts and what to do. A crisis-proof Austria in the event of a blackout is only possible with a BMI and a police force that can hold out,” the Minister of the Interior emphasised.

Among other things, the cooperation agreement covers:

  • information exchange and crisis communication
  • defining standardised procedures in the event of a blackout
  • carrying out risk assessments
  • producing situation reports
  • joint exercises as well as training and further training
  • state crisis and disaster management
  • protection of critical infrastructure

Resilient BMI sites

Minister of the Interior Nehammer also gave an insight into the ministry’s preparations for a blackout. 100 police sites are to be developed into resilient – i.e. able to hold out – sites. These include the ministry itself and important headquarters such as the Federal Criminal Police Office (BKA), the Directorate for State Protection and Intelligence (DSN), the Cobra special unit, the provincial police directorates and the district police commands.

These sites will be made immune to a blackout so that operations can be maintained. This concerns, for example, the emergency power supply and the possibility of reduced building services. In addition, refuelling of the vehicle fleet and the emergency generators must be ensured. In a crisis, key police personnel are to be brought together at these sites.

In addition, the authorities and the operators of critical infrastructure such as APG can fall back on their own communication channel. “This is a radio link that we use in a crisis in addition to satellite phones. All of these are important building blocks for an Austria with secure supply and are therefore part of our project and investment plan of around 3.5 billion euros until 2032 for a sustainable and secure electricity system,” said APG board member Gerhard Christiner.

Blackout preparedness
Power supply system
Crises / preparedness

Herbert Saurugg

For years I have been publishing extensive analyses of what happens in the event of a blackout on my website.

Since 2019, as part of our cooperation, my newsletters and blog posts have also been published here.

Read the post online (German)

My website (German)

Notes on content provided by authors

Comments

Loading comments …

Become a member to comment publicly. GAIA members write comments in the members' portal — under their nickname, visible to everyone.

Become a member Already a member? Comment in the portal →

Translate

Machine translation by Google Translate. The page address is only sent to Google once you click — privacy.